Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News Editorials & Other Articles General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

unhappycamper

(60,364 posts)
Fri Jun 21, 2013, 06:48 AM Jun 2013

U.S. Afghanistan auditor tells of free-for-all as subcontractors demand money they’re owed

http://www.mcclatchydc.com/2013/06/20/194529/us-afghanistan-auditor-tells-of.html#storylink=cpy



A half finished police watchtower in Afghanistan on Oct. 23, 2010

U.S. Afghanistan auditor tells of free-for-all as subcontractors demand money they’re owed
By Jay Price | McClatchy Foreign Staff
Posted on Thursday, June 20, 2013

KABUL, Afghanistan — The U.S. government’s primary auditing agency for Afghanistan has found that subcontractors on U.S.-funded projects in that country frequently aren’t paid, resulting in a litany of problems that include delayed and unfinished jobs, death threats to company workers and allegations of corruption among Afghan police and judicial officials.

Primary contractors are responsible for the failure, but because the nonpayments leave the impression that the U.S. government and coalition forces aren’t fulfilling their obligations, they undermine support for the coalition among the Afghan people and put at risk multimillion-dollar projects that are intended to promote stability, the Special Inspector General for Afghanistan Reconstruction said in a letter to U.S. diplomatic, defense and aid officials warning them of what it called “serious problems” of nonpayments.

The letter, which SIGAR also released publicly, said that one project funded by the U.S. Army Corp of Engineers to build police stations in northern Afghanistan was reduced in size after unpaid subcontractors walked away with equipment that belonged to the prime contractor.

"The prime contractor was removed from the project in May 2010, six months past the completion date with only an estimated 40 percent of the work completed," the letter said.